Loft conversion construction stages:
Week 1
Scaffolding erected. Water tanks moved. Steel beams installed. New floor joists constructed.
Week 2
Velux windows installed. If dormer required, then dormer shell constructed. If gable needed, then gable wall built up as per plans. Flat roof constructed.
Week 3
First installation of electrics, plumbing, and heating.
Week 4
Ceiling taken down above existing stairwell. New stairs fitted. Plasterboard and smooth plaster finish to underside of stairs.
Week 5
Partition walls erected, insulated and plastered. Second installation of electrics, plumbing and heating.
Week 6
The finishing touches. Carpentry work completed including architraves, skirtings and doors. Smoke alarms fitted. Final visit from local authority building control.