Loft conversion construction stages:

Week 1

Scaffolding erected. Water tanks moved. Steel beams installed. New floor joists constructed.

Week 2

Velux windows installed. If dormer required, then dormer shell constructed. If gable needed, then gable wall built up as per plans. Flat roof constructed.

Week 3

First installation of electrics, plumbing, and heating.

Week 4

Ceiling taken down above existing stairwell. New stairs fitted. Plasterboard and smooth plaster finish to underside of stairs.

Week 5

Partition walls erected, insulated and plastered. Second installation of electrics, plumbing and heating.

Week 6

The finishing touches. Carpentry work completed including architraves, skirtings and doors. Smoke alarms fitted. Final visit from local authority building control.

Payments staged throughout project, with final payment after all work is completed

We organise all planning and building regulations on your behalf

Call now on 0800 533 5821

How We Work

We work to a carefully planned schedule for the work we undertake here at NK Conversions, so take the time to peruse our week-by-week plan that culminates in you enjoying your new living space.

Projects can be completed in 5 to 7 weeks - Call us today on 0800 533 5821